WMS Implementation Checklist: 12 Steps to Go Live Without Disrupting Orders

By Vikashini
WMS implementation checklist for warehouse go-live

You are trying to move from spreadsheets to a new system but still have 300 orders to process every day. What happens if your stock levels are incorrect after migration? You don’t get orders from Amazon or Flipkart. You may ship incorrect items, oversell or miss dispatch times.

This WMS implementation checklist will guide you through 12 steps to get your warehouse ready, migrate your stock, ensure processes are tested and you can move systems without causing any disruption.

A WMS implementation involves setting up your software, ensuring your data is accurate, your integrations are working, your staff are trained and you have a go-live plan.

What is WMS Implementation?

WMS Implementation involves setting up your warehouse software. Warehouses typically use WMS to help with receiving, storing, tracking stock, picking, packing, dispatch and returns. This depends on what features your software offers.

Businesses will use warehouse management software to help reduce stock discrepancies, picking errors, manual updates and late orders.

If you have 50 units in your spreadsheet, but only 43 in your warehouse and incorrectly migrate your stock, you will start off with inaccurate data in your new system.

Understanding the difference between WMS and other business software:

SystemPurpose
WMSManages physical stock in your warehouse
OMSManages orders
ERPConnects financial, procurement and other areas of your business.

Whilst there may be some overlap, they are not interchangeable.

WMS Implementation Checklist

12-step WMS implementation checklist
StepActionOutcome
1Define Objectives and OwnershipProject plan
2Choose the right WMS softwareRequirements approved
3Map Warehouse ProcessesProcess maps
4Plan IntegrationsData flow plan
5Clean Stock DataVerified SKUs
6Set up warehouse rulesWarehouse set-up
7Prepare hardwareTested hardware
8Migrate stockOpening stock reconciled
9Train staffStaff trained
10Test processesUAT approved
11Run pilot and go-live planGo-live approved
12Go-live and monitorStable processes

Assign ownership to each step. Some can be done at the same time but make sure the key checks are done before going live.

1. Define Objectives and Ownership

Start by identifying what issues you have in your warehouse. Are staff picking the wrong items? Are you missing orders? Is your system showing stock that you don’t have?

Define what you want to achieve from your project. Maybe you want to reduce stock discrepancies, picking errors or increase on time dispatches.

Define what your project will cover. This includes the warehouses, SKUs, daily orders, sales channels and integrations you will need. Define who will be responsible for what:

RoleResponsibilities
Project OwnerBudget, timeline and decisions
Warehouse ManagerWarehouse processes
Inventory LeadStock records and counts
IT LeadIntegrations and hardware
Training LeadStaff training

Define how you will report and resolve issues.

You should have defined your objectives, responsibilities and success criteria.

2. Choose the Right WMS Software

Ensure your WMS software will work for your warehouse.

If you have 50 orders a day, your software requirements will be very different to a warehouse with 5000 orders and multiple locations.

Ensure the software you choose has the features you need:

FeatureConsider
Barcode ScanningCan staff scan items during receiving and picking?
Bin ManagementCan you track items by bin?
Order IntegrationCan orders be pulled from your OMS?
Batch TrackingCan you manage batches and expiry dates?
ReturnsCan staff log returned stock?
ReportingCan managers view stock and orders?

Don’t just look at the subscription price. You may have to pay for set-up, integrations, migration, scanners, printers and training. Ask vendors to show you how your processes would work in your warehouse. You should have chosen a software that covers your key requirements.

3. Map Processes

Before making any changes you need to understand how your warehouse currently works.

Define how your items are received, stored, picked and prepared for dispatch.

ProcessCurrent MethodProposed Method
ReceivingManual entriesScanner to verify stock
PutawayStaff know where to place itemsBin records
PickingPrinted ordersDigital picking
PackingManual checkingBarcode scanning
DispatchManual updatesIntegrated shipping updates

Your WMS software should be able to support your catalogue, order volume and fulfilment requirements.

For example, if your staff are currently printing orders and manually searching for items, having a scanning process will help them verify items whilst picking. Don’t try to change all processes at once.

You should have approval from your warehouse manager for current and new processes.

4. Plan Integrations

Your warehouse will need to pull in data from other systems.

You may be receiving orders from Amazon, Flipkart, Shopify and your website. Your stock and shipping updates also need to go to the right place.

Your WMS software will need to pull in the right data from your OMS, ERP and shipping systems.

DataFromTo
New OrdersOMSWMS
Stock UpdatesWMSOMS / ERP
Dispatch StatusWMS / ShippingOMS
TrackingShippingOMS
Returns ReceivedWMSOMS / ERP

Depending on your set-up you may have data going in different directions. Define what system will be responsible for each piece of information.

Test what happens if your integrations fail, duplicate messages, delayed updates and incorrect SKUs. For example, if your WMS records a sale but the stock update doesn’t reach Flipkart, your listing may still show stock that has already been sold.

You should have defined your integrations, data and error handling processes.

5. Clean Stock Data

WMS stock data cleaning checklist

Just because you are moving to a new system doesn’t mean incorrect data will be correct. Before migrating your stock, check your SKUs, item names, barcodes, stock levels, units and warehouse locations. Also check your reserved, damaged and unsellable stock.

A warehouse stock management system will require accurate item identification and locations.

IssueExampleResolution
Duplicate SKU2 items with SKU-101Unique identifiers
No BarcodeUnable to scan itemCreate or map barcode
Incorrect Stock LevelShows 120 in system but only 112 in stockInvestigate discrepancy
Incorrect LocationItem in Bin C but shows in Bin ACorrect location
Damaged StockDamaged items included in sellable stockSeparate stock statuses

Don’t change stock levels unless you have investigated why there is a discrepancy. Make a back-up of your original records. Your products and stock data should now be verified and ready to migrate.

6. Set Up Warehouse Locations and Rules

Your WMS should reflect your warehouse. Set up your warehouses, zones, aisles, racking, shelves and bins.

Many warehouse systems have location codes to make it easier for staff to find and move items.

Set up processes for:

  • Receiving and storage
  • Static or dynamic putaway
  • Single or batch picking
  • Stock statuses
  • Permissions

For example, if your warehouse is for clothing you may need to have variations for sizing and colour. If your warehouse is for food you may need to have batch and expiry dates. Not all WMS will have advanced picking or automatic putaway.

Test your set-up using real SKUs and locations. Your warehouse locations, stock statuses and permissions should be working.

7. Prepare Scanners, Printers and Infrastructure

Even if your software is perfect, if your label printer breaks you will miss orders.

Before going live check your:

EquipmentCheck
Barcode ScannerCan scan the right item and location codes
Label PrinterClear labels with the right size
Mobile DeviceCan complete tasks
Warehouse Wi-FiCan be used for receiving, storage and dispatch
Packing StationCan view orders and shipment information
Back-upCan be used for your agreed outage process

Test your devices in the actual locations your staff will be using. For example, your scanner may work near your office but not in a far away storage area. Ensure you have back-up devices for key processes. Your devices, labels and connectivity should be working.

8. Migrate Stock

WMS stock migration and reconciliation process

This is one of the most risky parts of your project. You will be moving your item records, locations, stock levels, reserved items and possibly partial orders.

Follow a controlled process:

  • Agree a cut-off time.
  • Export verified records.
  • Identify any open, picked and dispatched orders.
  • Note any reserved items.
  • Complete stock verification.
  • Import into your new WMS.
  • Compare stock levels and locations.
  • Investigate any discrepancies.
  • Check stock statuses.
  • Approve opening balances.

Example of Stock Reconciliation:

SKUOld SystemPhysical StockNew WMSStatus
SKU-101120118118Matches Physical Stock
SKU-102757575Matches
SKU-103484545Matches Physical Stock
SKU-104200200198Discrepancy

SKU-101 and SKU-103 match the verified physical stock in your new WMS. However, you should still note why the old data was incorrect.

SKU-104 has an issue with the migration. There are 200 items in your warehouse but only 198 in your new system. Investigate why there are 2 missing items before going live.

Ensure items are in the right bins and reserved items are accounted for.

Your opening stock should match the verified stock levels, locations and relevant stock statuses.

9. Train Staff

Your staff may understand your old process but not your new software.

Train each team on what they need to do:

TeamTraining
ReceivingLog items and discrepancies
PutawayScan locations and move items
PickingComplete orders and missing items
PackingVerify items and print labels
InventoryCount and adjust stock
SupervisorsMonitor and resolve issues

Use practical examples. For example, ask your picker to complete an order but the item they need isn’t in the right bin.

Define how they should complete the process. Your staff should be able to complete their processes with little support.

10. Test End-to-End Processes

WMS user acceptance testing workflow

Don’t just test individual screens. Ensure you can complete an order from start to finish.

This is known as User Acceptance Testing (UAT).

Test normal processes and also any exceptions. For example cancelled orders, missing items, incorrect barcodes, damaged returns and failed integrations.

TestExpected OutcomeResult
Single Item OrderCorrect SKU sentPass
Incorrect BarcodeReject item if set upPass
Stock MoveBoth locations updatedPass
Cancelled OrderRemove from active pickingPass
Failed Stock UpdateError identified and recoveredFail

If your stock update fails, you may oversell. Assign someone to fix the issue and re-test.

Try to include busy order scenarios if possible. All of your key processes should be passing with no blocking issues.

11. Run Pilot and Go Live Plan

Before going live with your whole warehouse try a small pilot. Maybe start with one zone, certain SKUs or a low volume of orders.

This will help you identify any issues. If you are replacing your current WMS systems be careful not to have both systems reserving the same stock.

Your go-live plan should include the time to go live, final data export, open orders, stock reconciliation, integration activation and testing your first live order.

Assign someone to approve each process. Also have a back-up plan. What will you do if you stop receiving orders or can’t generate shipping labels? Define when you should pause your go-live and how you will account for any transactions. You should have approved your pilot results and have a go-live and back-up plan.

12. Go Live and Monitor

Going live doesn’t mean your project is finished. Monitor your orders, stock, picking, packing, dispatch and any system errors for the first few days.

Monitor the following KPIs:

KPIDescription
Stock AccuracyStock in system vs physical stock
Picking AccuracyCorrect items picked
On Time DispatchOrders dispatched on time
Order Processing TimeTime taken to process orders
Integration FailuresFailed data transfers
Stock AdjustmentsFrequency of stock adjustments

Compare to your objectives from step 1. Review any issues daily during the initial go-live. Assign ownership to any unresolved issues.

Your key processes should be stable and you know who is responsible for providing support.

How Long Does WMS Implementation Take?

The time it takes to implement your WMS will depend on the size of your warehouse, quality of stock, integrations and how prepared your staff are.

Below is an example of a project taking 8 weeks:

WeekKey Activity
1Define Objectives and Ownership
2Evaluate Software and Map Processes
3Plan Integrations and Clean Data
4Set up Warehouse Processes
5Prepare Hardware and Test Migration
6Train Staff and UAT
7Fix Issues and Run Pilot
8Complete Migration and Go Live

This is an example and can vary. If you have complex integrations, a large number of SKUs and poor quality stock it may take longer.

Allow extra time for testing and unexpected issues.

Final WMS Go Live Readiness Checklist

WMS go-live readiness checklist
ReadinessComplete
Project scope and ownership approved☐
Software requirements met☐
Warehouse processes mapped☐
Integrations tested☐
SKU data verified☐
Locations set up☐
Scanners and printers tested☐
Stock reconciled☐
Open orders accounted for☐
Staff trained☐
Key UAT tests passed☐
Pilot completed☐
Go-live plan approved☐
Back-up processes in place☐
Monitoring team assigned☐

Don’t just verbally approve your go-live. Ensure you have a record of who has completed each check. Ensure any key issues are resolved.

Common WMS Implementation Mistakes

MistakeImpactHow to Avoid
Incorrect Stock MigrationStock discrepanciesVerify data
Not considering current processesConfusionMap processes
Not testing all integrationsMissed updatesTest end-to-end processes
Not accounting for open ordersDouble fulfilmentReview any open orders
Not training staffPicking errorsUse practical examples
Not running a pilotUnexpected issuesControlled testing
No back-up planLonger disruptionPlan recovery processes
Stop monitoring too soonRepeated errorsReview performance

Don’t rush your go-live. Having incorrect stock and causing disruptions can cause more issues than a short delay.

How Base OMS Can Help Manage Integrated Ecommerce Processes

OMS and WMS integration for ecommerce fulfilment

If you are selling on Amazon, Flipkart, Shopify and other supported channels it can take time to manage your orders.

Base OMS can help ecommerce businesses manage integrated orders, stock and fulfilment processes. It can help with order processing and stock visibility for supported sales channels.

For example, your warehouse may have a dedicated WMS to manage physical stock but your OMS will manage your orders and stock updates. Both systems will need accurate information.

Base OMS shouldn’t be used as a replacement for all the specific features of a WMS. Depending on your warehouse system, it may be compatible.

Find out how Base OMS can help you manage your orders and stock from one place.

Conclusion

Having accurate stock, clear processes, working integrations and trained staff will help you have a successful implementation.

Use this WMS implementation checklist to get your systems ready, test your processes and manage your transition.

Don’t rush your go-live. Ensure orders are flowing correctly and your stock is accurate.

Base OMS can help you manage your orders and stock for supported ecommerce channels.

FAQs

What is a WMS Implementation Checklist?

A checklist of actions to complete when implementing warehouse software. This includes planning, migrating stock, integrations, training and monitoring your go-live.

What are the key steps in implementing a WMS?

Planning, choosing software, mapping processes, preparing data, setting up warehouse, migrating stock, training staff, testing and going live.

How long does it take to implement a WMS?

This will depend on the size of your warehouse, complexity of stock and integrations. A simple setup may take less time than a multi-warehouse.

What should I prepare before implementing a WMS?

Prepare your SKUs, stock levels, warehouse locations, processes, integration requirements and staff responsibilities.

How much does it cost to implement a WMS?

This will depend on the software, set-up, integrations, migration, hardware and training. Ask for a detailed breakdown.

What is the difference between a WMS and OMS?

A WMS manages physical processes in your warehouse. An OMS manages orders across sales channels.

How do I migrate my stock?

Clean your product data, verify your physical stock, export your data, import into your new system and reconcile your opening stock.

Can I implement a WMS without causing any disruption to orders?

You can reduce disruption by having a controlled migration, testing, training and a good go-live plan. There may still be some disruption.

What integrations does WMS software require?

Common integrations include OMS, ERP, ecommerce, marketplaces and shipping. This depends on your business requirements.

How do I test my WMS?

Test receiving, picking, packing, dispatch, returns, stock updates and integration failures using realistic scenarios.

What is UAT?

User Acceptance Testing ensures your staff can complete real processes in your warehouse.

Should I run my old and new WMS together?

Running them in parallel can help but you need controls in place to avoid double allocation of stock and orders.

What are the main risks of implementing a WMS?

Incorrect stock, missing orders, failed integrations, not training staff and not testing fully.

How do I measure success of my WMS implementation?

Monitor your stock accuracy, picking errors, order processing time, on time dispatch and integration failures.